Earth Pressure Behind A Retaining Wall

Status:  Complete
Report Date:  03/21/2005

Summary:

Earth pressure cells, tiltmeters, strain gages, inclinometer casings, and survey reflectors were installed in fall 2002 during construction of a 26-ft (7.9-m) high Minnesota Department of Transportation (Mn/DOT) reinforced concrete cantilever retaining wall. A data acquisition system with remote access monitored some 60 sensors on a continual basis. Analyses of the data indicated the development of active earth pressure at the end of backfilling, with a resultant at about one-third of the backfill height. Translation of 0.45 in. (11 mm), or about 0.1% of the backfill height, was responsible for development of the active condition. The wall also rotated 0.03